Water Hazards and Inundation Accidents in Mines – Causes, DGMS Regulations & Prevention

Water Hazards and Inundation Accidents in Mines – Causes, DGMS Regulations & Prevention

Water Hazards & Inundation

1. Introduction

Water hazards are among the most dangerous threats in underground and opencast mines. Sudden inundation can lead to heavy loss of life and property. DGMS treats such accidents with utmost seriousness, and special statutory provisions exist under CMR 2017 (Reg. 172–175) to prevent and investigate these hazards.

2. Causes of Water Inflow and Inundation

A. Natural Causes

  • Old waterlogged workings: Undetected adjacent old mines containing accumulated water.
  • Surface water entry: Heavy rainfall, river diversion failures, or cracks in strata allowing inflow.
  • Groundwater seepage: Through faults, joints, or permeable strata.
  • Subsidence or collapse: Opening paths for water to enter from surface or aquifers.

B. Man-made Causes

  • Improper exploration: Inadequate borehole drilling before approaching old workings.
  • Negligence: Ignoring water warnings or failure to plug boreholes.
  • Faulty barrier estimation: Reduced safety thickness due to poor surveying.
  • Mechanical failures: Failure of pumps, pipelines, or power supply.

3. DGMS Statutory Provisions – CMR 2017

Regulation Provision Summary
Reg. 172 Precautions against danger from surface water. Proper drainage and embankment required.
Reg. 173 Precautions against danger from underground water. Mandatory boreholes and barrier maintenance.
Reg. 174 Precautions during connection with water-logged workings. Only with written permission of manager and plan verification.
Reg. 175 Procedure for investigation of inundation accidents. Reporting to DGMS, inquiry, and preventive review.

4. Preventive Measures

  • Planning Stage: Proper geological survey, boreholes drilled ahead of workings, maintain minimum 15m safety barrier, and prepare water danger plans.
  • Operation Stage: Regular monitoring of inflow, high-capacity and standby pumps, inspection of embankments, and use of sand stowing.
  • Emergency Stage: Use of high-capacity submersible pumps, clear evacuation routes, refuge chambers, and regular mock drills.

5. DGMS Case Studies (Examples)

Chasnala Disaster (1975, Bihar):

Cause: Breach of barrier between working mine and old waterlogged mine. Casualties: 375. Lesson: Strict compliance with Reg. 173 & 174 mandatory.

Kujama Mine (Jharkhand, 1996):

Cause: Unplugged boreholes led to sudden inflow. Lesson: Boreholes must be properly sealed after use.

Raniganj Coalfield Case:

Cause: Fault zone connection to aquifer. Lesson: Hydrogeological mapping is critical.

6. Investigation Procedure after Inundation (Reg. 175)

Report accident immediately to DGMS, stop operations, conduct a joint inquiry, and prepare a technical report with causes and remedial actions. Lessons learned are circulated for future prevention.

⚡ Quick One-Liners (Revision Points)

  1. Reg. 172–175 of CMR 2017 deal with water hazards.
  2. Minimum 15 m barrier must be left between old and new workings.
  3. Chasnala disaster (1975) was due to water inundation.
  4. DGMS approval needed before connecting with waterlogged mine.
  5. Pumps must have standby capacity of 50% or more.
  6. All boreholes must be properly sealed after use.
  7. Emergency drills must be held once every 3 months.

🧾 Descriptive Model Answer

Q. Describe the causes and preventive measures of water inundation in mines as per CMR 2017.

Answer: Water inundation in mines occurs when uncontrolled inflow of surface or underground water floods mine workings. The main causes include old waterlogged workings, inadequate borehole drilling, poor barrier estimation, heavy rainfall, and mechanical pump failure. As per CMR 2017 Regulations 172–175, the Manager must take adequate precautions against surface and underground water, including: drilling exploratory boreholes, maintaining a safety barrier (min 15m), ensuring effective drainage, preparing a water danger plan, and conducting regular inspections and mock drills. In case of an inundation accident, it must be reported immediately to the DGMS and investigated as per Reg. 175.

🎯 Test Your Knowledge: 25 MCQs

Q1. Which CMR 2017 regulation deals with precautions against surface water?

A. Reg. 172
B. Reg. 173
C. Reg. 174
D. Reg. 175

Q2. The minimum safety barrier between two waterlogged workings is:

A. 5 m
B. 10 m
C. 15 m
D. 20 m

Q3. Which disaster led to major reforms in water hazard prevention in India?

A. Raniganj Fire
B. Chasnala Disaster
C. Dhanbad Explosion
D. Bhanegaon Flood

Q4. Inundation from old workings is mainly due to:

A. Gas outburst
B. Faulty ventilation
C. Improper borehole drilling
D. Poor lighting

Q5. DGMS requires boreholes to be drilled ahead of the face when approaching suspected water within:

A. 10 m
B. 15 m
C. 30 m
D. 60 m

Q6. Regulation 173 deals with:

A. Surface water
B. Underground water
C. Pumping
D. Safety officers

Q7. Which of the following is a preventive measure?

A. Ignoring water seepage
B. Reducing barrier thickness
C. Hydrogeological survey
D. Removing sump

Q8. Which equipment is most essential during inundation?

A. Belt conveyor
B. Pumping set
C. Roof bolter
D. Drill jumbo

Q9. Reporting of inundation accident is required under which regulation?

A. Reg. 172
B. Reg. 174
C. Reg. 175
D. Reg. 177

Q10. The water danger plan is prepared by:

A. Surveyor
B. Manager
C. Safety Officer
D. Overman

Q11. Water hazard is classified as:

A. Electrical accident
B. Mechanical hazard
C. Natural hazard
D. Fire hazard

Q12. The purpose of boreholes in water-prone areas is to:

A. Drain air
B. Detect water
C. Support roof
D. Store explosives

Q13. Which of the following is not a cause of inundation?

A. Old waterlogged workings
B. Fault zones
C. Poor pumping system
D. Proper borehole survey

Q14. Minimum frequency for mock drills against inundation is:

A. Monthly
B. Quarterly
C. Half-yearly
D. Yearly

Q15. The first step during water inflow is:

A. Stop power
B. Evacuate workers
C. Start loading
D. Continue working

Q16. Which of the following is a DGMS-approved barrier reduction method?

A. Oral permission
B. Joint inspection and written approval
C. Verbal assurance
D. Pumping plan

Q17. The Chasnala disaster was due to:

A. Gas explosion
B. Fire
C. Water inundation
D. Roof fall

Q18. Regulation 175 relates to:

A. Accident reporting
B. Pumping operations
C. Roof support
D. Mine ventilation

Q19. Inundation due to heavy rain is linked to:

A. Underground water
B. Surface water
C. Mine gas
D. Fire

Q20. Boreholes should be:

A. Horizontal only
B. Inclined and ahead of face
C. Random
D. Vertical only

Q21. Main statutory responsibility for water hazard prevention lies with:

A. DGMS
B. Safety Officer
C. Manager
D. Owner

Q22. Pumping capacity should be sufficient to:

A. Match inflow
B. Double inflow
C. Handle peak inflow + standby
D. Be minimal

Q23. Investigation of inundation includes:

A. Geological mapping
B. Accident cause analysis
C. Safety recommendations
D. All of the above

Q24. Who must approve barrier reduction below 15 m?

A. DGMS
B. Safety Officer
C. Mine Owner
D. Local Inspector

Q25. The purpose of stowing in old galleries is:

A. Support roof
B. Prevent water seepage
C. Store materials
D. Increase ventilation

Q1. Which CMR 2017 regulation deals with precautions against surface water?

A. Reg. 172
B. Reg. 173
C. Reg. 174
D. Reg. 175

Q2. The minimum safety barrier between two waterlogged workings is:

A. 5 m
B. 10 m
C. 15 m
D. 20 m

Q3. Which disaster led to major reforms in water hazard prevention in India?

A. Raniganj Fire
B. Chasnala Disaster
C. Dhanbad Explosion
D. Bhanegaon Flood

Q4. Inundation from old workings is mainly due to:

A. Gas outburst
B. Faulty ventilation
C. Improper borehole drilling
D. Poor lighting

Q5. DGMS requires boreholes to be drilled ahead of the face when approaching suspected water within:

A. 10 m
B. 15 m
C. 30 m
D. 60 m

Q6. Regulation 173 deals with:

A. Surface water
B. Underground water
C. Pumping
D. Safety officers

Q7. Which of the following is a preventive measure?

A. Ignoring water seepage
B. Reducing barrier thickness
C. Hydrogeological survey
D. Removing sump

Q8. Which equipment is most essential during inundation?

A. Belt conveyor
B. Pumping set
C. Roof bolter
D. Drill jumbo

Q9. Reporting of inundation accident is required under which regulation?

A. Reg. 172
B. Reg. 174
C. Reg. 175
D. Reg. 177

Q10. The water danger plan is prepared by:

A. Surveyor
B. Manager
C. Safety Officer
D. Overman

Q11. Water hazard is classified as:

A. Electrical accident
B. Mechanical hazard
C. Natural hazard
D. Fire hazard

Q12. The purpose of boreholes in water-prone areas is to:

A. Drain air
B. Detect water
C. Support roof
D. Store explosives

Q13. Which of the following is not a cause of inundation?

A. Old waterlogged workings
B. Fault zones
C. Poor pumping system
D. Proper borehole survey

Q14. Minimum frequency for mock drills against inundation is:

A. Monthly
B. Quarterly
C. Half-yearly
D. Yearly

Q15. The first step during water inflow is:

A. Stop power
B. Evacuate workers
C. Start loading
D. Continue working

Q16. Which of the following is a DGMS-approved barrier reduction method?

A. Oral permission
B. Joint inspection and written approval
C. Verbal assurance
D. Pumping plan

Q17. The Chasnala disaster was due to:

A. Gas explosion
B. Fire
C. Water inundation
D. Roof fall

Q18. Regulation 175 relates to:

A. Accident reporting
B. Pumping operations
C. Roof support
D. Mine ventilation

Q19. Inundation due to heavy rain is linked to:

A. Underground water
B. Surface water
C. Mine gas
D. Fire

Q20. Boreholes should be:

A. Horizontal only
B. Inclined and ahead of face
C. Random
D. Vertical only

Q21. Main statutory responsibility for water hazard prevention lies with:

A. DGMS
B. Safety Officer
C. Manager
D. Owner

Q22. Pumping capacity should be sufficient to:

A. Match inflow
B. Double inflow
C. Handle peak inflow + standby
D. Be minimal

Q23. Investigation of inundation includes:

A. Geological mapping
B. Accident cause analysis
C. Safety recommendations
D. All of the above

Q24. Who must approve barrier reduction below 15 m?

A. DGMS
B. Safety Officer
C. Mine Owner
D. Local Inspector

Q25. The purpose of stowing in old galleries is:

A. Support roof
B. Prevent water seepage
C. Store materials
D. Increase ventilation

Q1. Which CMR 2017 regulation deals with precautions against surface water?

A. Reg. 172
B. Reg. 173
C. Reg. 174
D. Reg. 175

Q2. The minimum safety barrier between two waterlogged workings is:

A. 5 m
B. 10 m
C. 15 m
D. 20 m

Q3. Which disaster led to major reforms in water hazard prevention in India?

A. Raniganj Fire
B. Chasnala Disaster
C. Dhanbad Explosion
D. Bhanegaon Flood

Q4. Inundation from old workings is mainly due to:

A. Gas outburst
B. Faulty ventilation
C. Improper borehole drilling
D. Poor lighting

Q5. DGMS requires boreholes to be drilled ahead of the face when approaching suspected water within:

A. 10 m
B. 15 m
C. 30 m
D. 60 m

Q6. Regulation 173 deals with:

A. Surface water
B. Underground water
C. Pumping
D. Safety officers

Q7. Which of the following is a preventive measure?

A. Ignoring water seepage
B. Reducing barrier thickness
C. Hydrogeological survey
D. Removing sump

Q8. Which equipment is most essential during inundation?

A. Belt conveyor
B. Pumping set
C. Roof bolter
D. Drill jumbo

Q9. Reporting of inundation accident is required under which regulation?

A. Reg. 172
B. Reg. 174
C. Reg. 175
D. Reg. 177

Q10. The water danger plan is prepared by:

A. Surveyor
B. Manager
C. Safety Officer
D. Overman

Q11. Water hazard is classified as:

A. Electrical accident
B. Mechanical hazard
C. Natural hazard
D. Fire hazard

Q12. The purpose of boreholes in water-prone areas is to:

A. Drain air
B. Detect water
C. Support roof
D. Store explosives

Q13. Which of the following is not a cause of inundation?

A. Old waterlogged workings
B. Fault zones
C. Poor pumping system
D. Proper borehole survey

Q14. Minimum frequency for mock drills against inundation is:

A. Monthly
B. Quarterly
C. Half-yearly
D. Yearly

Q15. The first step during water inflow is:

A. Stop power
B. Evacuate workers
C. Start loading
D. Continue working

Q16. Which of the following is a DGMS-approved barrier reduction method?

A. Oral permission
B. Joint inspection and written approval
C. Verbal assurance
D. Pumping plan

Q17. The Chasnala disaster was due to:

A. Gas explosion
B. Fire
C. Water inundation
D. Roof fall

Q18. Regulation 175 relates to:

A. Accident reporting
B. Pumping operations
C. Roof support
D. Mine ventilation

Q19. Inundation due to heavy rain is linked to:

A. Underground water
B. Surface water
C. Mine gas
D. Fire

Q20. Boreholes should be:

A. Horizontal only
B. Inclined and ahead of face
C. Random
D. Vertical only

Q21. Main statutory responsibility for water hazard prevention lies with:

A. DGMS
B. Safety Officer
C. Manager
D. Owner

Q22. Pumping capacity should be sufficient to:

A. Match inflow
B. Double inflow
C. Handle peak inflow + standby
D. Be minimal

Q23. Investigation of inundation includes:

A. Geological mapping
B. Accident cause analysis
C. Safety recommendations
D. All of the above

Q24. Who must approve barrier reduction below 15 m?

A. DGMS
B. Safety Officer
C. Mine Owner
D. Local Inspector

Q25. The purpose of stowing in old galleries is:

A. Support roof
B. Prevent water seepage
C. Store materials
D. Increase ventilation

Prepare for DGMS Exams with India’s 1st Online Mining Academy

Download Notes | Practice MCQs | Crack DGMS Manager’s Exam

Visit www.onlineminingexam.com

Call/WhatsApp: 9971114020


Online Mining Exam
A California-based travel writer, lover of food, oceans, and nature.

OUR COURSES View More