Q1. DGMS (Tech.) Circular No. 02 of 2010 deals with: A. Blasting practices in opencast mines B. Systematic slope monitoring C. Mine ventilation standards D. Explosives handling procedures E. Transport rules in opencast mines ✅ Answer: B Explanation: Circular 02/2010 specifically prescribes Systematic Slope Monitoring (SSM) in opencast mines.
Q2. The main objective of slope monitoring is: A. Increase mine production B. Ensure early detection of slope instability C. Reduce manpower requirement D. Replace geotechnical studies E. Reduce overburden removal ✅ Answer: B Explanation: The goal is early warning and prevention of slope failures, not production-related.
Q3. The slope monitoring programme (SMP) must include: A. Only blasting vibration studies B. Only annual geotechnical survey C. Visual, instrumentation, and geotechnical monitoring D. Only prism monitoring E. None of the above ✅ Answer: C Explanation: SMP must integrate visual inspection, scientific instrumentation, and geotechnical design inputs.
Q4. Which instrument is used to monitor pore water pressure in slope mass? A. Inclinometer B. Extensometer C. Piezometer D. LiDAR E. Seismograph ✅ Answer: C Explanation:Piezometers → measure pore water pressure, which directly affects slope stability.
Q5. For working slopes, the minimum Factor of Safety (FoS) should be: A. 1.0 B. 1.1 C. 1.2 D. 1.5 E. 2.0 ✅ Answer: C Explanation: DGMS requires FoS ≥ 1.2 for working slopes, ≥ 1.5 for final pit slopes.
Q6. Which of the following is NOT a tool for slope monitoring? A. Total Station B. Inclinometer C. Extensometer D. Piezometer E. Flameproof switchgear ✅ Answer: E Explanation: Flameproof switchgear is for electrical safety, not slope monitoring.
Q7. Frequency of visual inspection by mine officials should be: A. Daily (shift-wise) B. Weekly C. Monthly D. Quarterly E. Annually ✅ Answer: A Explanation: Shift-wise/daily visual monitoring is compulsory.
Q8. Comprehensive slope stability assessment by a scientific agency should be carried out: A. Weekly B. Monthly C. Annually D. Every 5 years E. Only at mine closure ✅ Answer: C Explanation: Annual slope stability study is mandatory.
Q9. External dump slope monitoring is essential because: A. Dumps are consolidated rock B. Dumps consist of loose, unconsolidated material C. Dumps are less dangerous than pit slopes D. Dumps are always stable E. Dumps don’t require monitoring ✅ Answer: B Explanation:Loose dumps are prone to failures, hence systematic monitoring is required.
Q10. A common early sign of slope failure is: A. Sudden rise in production B. Development of tension cracks C. Reduction in water seepage D. Increase in ore grade E. None of the above ✅ Answer: B Explanation:Cracks at slope crest are classic early indicators of instability.
Q11. Which technology provides real-time slope movement detection? A. Total station B. Ground-based radar (GBR) C. Compass survey D. Tape measurement E. Barometer ✅ Answer: B Explanation:GBR detects slope movement in real-time with high accuracy.
Q12. Catch benches are provided in slopes mainly for: A. Drainage of water B. Stopping rockfalls and sliding material C. Supporting haul roads D. Allowing machinery parking E. Increasing slope angle ✅ Answer: B Explanation:Catch benches intercept falling material and improve slope safety.
Q13. In slope monitoring, LiDAR technology is used for: A. Measuring pore pressure B. Mapping 3D slope surfaces C. Detecting vibrations D. Studying blasting fumes E. Checking machine health ✅ Answer: B Explanation: LiDAR produces 3D terrain/slope models for deformation studies.
Q14. Who holds overall responsibility for slope monitoring in a mine? A. Overman B. Surveyor C. Mine Manager D. Geotechnical Engineer E. DGMS Inspector ✅ Answer: C Explanation:Mine Manager is legally responsible, though technical support is from surveyor & geotechnical expert.
Q15. Which condition is most dangerous for slope stability? A. Dry summer B. Heavy rainfall with poor drainage C. Winter season D. Controlled blasting E. Final slope benched ✅ Answer: B Explanation: Rain increases pore water pressure → slope failure risk.
Q16. In systematic slope monitoring, survey records must include: A. Bench height & slope angle B. Type of explosives used C. Output per shift D. Workers’ attendance E. Fuel consumption ✅ Answer: A Explanation: Bench geometry + slope stability parameters must be recorded.
Q17. A slope with FoS = 1.0 indicates: A. Stable condition B. Marginally stable, failure possible C. Very safe slope D. Excessively safe slope E. Not applicable ✅ Answer: B Explanation: FoS = 1.0 → resisting = driving forces → slope is critically stable.
Q18. Dump benches should normally be: A. 1–2 m B. 6–10 m C. 20–30 m D. 40–50 m E. Not benched at all ✅ Answer: B Explanation: DGMS recommends 6–10 m benches in OB dumps.
Q19. In case of slope movement detection, first action should be: A. Continue operations B. Evacuate men & machinery C. Increase excavation rate D. Reduce blasting charge E. Do nothing until failure occurs ✅ Answer: B Explanation: Immediate withdrawal of men & machines is the first emergency action.
Q20. Which circular mandates slope monitoring in Indian opencast mines? A. DGMS Tech. 01/2005 B. DGMS Tech. 02/2010 C. DGMS Tech. 03/2019 D. DGMS Tech. 04/2015 E. MMR 1961 Rule 190A ✅ Answer: B Explanation:02/2010 is the slope monitoring circular.
Q21. Controlled blasting near final slopes is required to: A. Improve coal grade B. Minimize slope disturbance C. Increase slope angle D. Reduce haul road length E. Increase powder factor ✅ Answer: B Explanation:Controlled blasting reduces vibrations → prevents slope weakening.
Q22. Slope Monitoring Cell in a mine is constituted under the: A. DGMS Inspector B. Surveyor C. Mine Manager D. IBM Authority E. Mining Engineer at DGMS HQ ✅ Answer: C Explanation:Mine Manager forms a slope monitoring cell as per circular.
Q23. Which is a non-instrumental method of slope monitoring? A. Prism survey B. Extensometer C. Visual observation D. Inclinometer E. Piezometer ✅ Answer: C Explanation: Visual inspection is a basic non-instrumental method.
Q24. Emergency Action Plan (EAP) for slope failure should include: A. Safe withdrawal, alarm, communication B. Production schedule revision C. Mine closure proposal D. Increase in manpower E. Only DGMS reporting ✅ Answer: A Explanation: EAP includes safe evacuation, alarm system, communication & mock drills.
Q25. The biggest advantage of systematic slope monitoring is: A. Higher output per man shift B. Reduced diesel consumption C. Early warning → prevention of slope failure D. Reduction in blasting cost E. Lesser haul road maintenance ✅ Answer: C Explanation: The ultimate purpose is early detection of instability → save lives + property.