🏭 DGMS Factory Inspection & Audit Checklist – Appendix XIX 

Factory inspection is a mandatory step before DGMS grants approval for:
  • Flameproof equipment
  • Intrinsically safe equipment
  • Gas detectors
  • Electrical machinery
  • PPE & safety devices
  • Importer-based equipment
DGMS verifies whether the manufacturer’s production system matches the approved design, standards & safety requirements. Appendix XIX of the DGMS Approval Policy explains exact factory audit points, which we decode below in simple OME style.

πŸ”Ή 1. Purpose of DGMS Factory Inspection DGMS conducts factory audits to ensure:

βœ” Correct manufacturing practices
βœ” Consistency with technical drawings
βœ” Proper quality & safety checks
βœ” Calibration of testing equipment
βœ” Good traceability system
βœ” No unauthorized modification
βœ” Adequate test facilities
βœ” Controlled production environment

πŸ”Ή 2. When Is DGMS Factory Audit Mandatory?

A factory audit is needed in: 

1) New DGMS Approval Before issuing approval for the first time.

2) Renewal (Every 3 Years) To verify consistent quality.

3) Suspension / Complaint Cases On receiving field complaints.

4) Imported Equipment (IAR Audit) DGMS inspects service facilities of the Indian Authorized Representative.

πŸ”Ή 3. Components of DGMS Factory Audit (Appendix XIX) 

 A DGMS audit covers 8 major sections:

⭐ 1) Quality Management System (QMS) DGMS checks:
  • ISO 9001 compliance
  • QMS manual
  • Quality policy
  • Organizational structure
  • Document control
  • Corrective & preventive action (CAPA) system
All processes must be documented.

⭐ 2) Manufacturing Infrastructure DGMS verifies:
  • Machinery & tools
  • Flameproof machining facilities
  • CNC machines
  • Winding machines
  • PCB assembly line (for IS equipment)
  • Painting/finishing
  • Assembly line layout
Equipment must match the approved drawings.

⭐ 3) Flameproof (FLP) Production Facilities DGMS checks:
  • Flamepath machining capability
  • Surface finish (Ra ≀ 6.3 ΞΌm)
  • Dimensional gauges
  • Torque-controlled tightening tools
  • Thread gauges
  • Air pressure test setups
Over 60% rejections occur due to poor flamepath machining.

⭐ 4) Testing Infrastructure Factories must have: For FLP Equipment:
  • Flamepath gauges
  • Pressure test chamber
  • Vernier/micrometers
  • Temperature meters
  • Gap measuring tools
For IS Equipment:
  • Oscilloscopes
  • Calibrated multimeters
  • Component testers
  • Thermal chamber
General Tests:
  • HV tester
  • IP test setup
  • Earth resistance meter

⭐ 5) Calibration System DGMS verifies:
  • Calibration register
  • Traceability to NABL/NIST
  • Periodic calibration
  • Stickers on equipment
Uncalibrated testing equipment = automatic rejection.

⭐ 6) Material Traceability & Stores Every part must be traceable to:
  • Batch number
  • Supplier certificate
  • Material grade
  • Inspection report
  • Raw material acceptance
DGMS checks whether materials used = material in technical drawings.

⭐ 7) Quality Control Records Factory must maintain:
  • Incoming inspection reports
  • In-process inspection
  • Routine test results
  • Final inspection checklist
  • Non-conformance records (NCR)
  • CAPA reports
DGMS ensures all products are batch-tested before dispatch.

⭐ 8) Compliance with Approved Drawings The most important part: 

❌ ANY deviation from drawing = Rejection
Examples:
  • Flamepath dimensions changed
  • Material changed
  • PCB design modified
  • Thickness variations
  • Fastener grade change
Only DGMS-approved drawings must be in production.

πŸ”Ή 4. DGMS Factory Audit Procedure

DGMS Issues Audit Notice ↓ Manufacturer Prepares Documents ↓ DGMS Inspection Team Visits Factory ↓ Verification of QMS, Testing & Production ↓ Check Against Appendix XIX Checklist ↓ Non-Conformity Report (if any) ↓ Corrective Action by Manufacturer ↓ Audit Clearance Issued If non-conformity is not resolved β†’ DGMS rejects/withdraws approval.

πŸ”Ή 5. Documents Required During DGMS Factory Audit
  • ISO 9001 certificate
  • QAR/QAN
  • Calibration certificates
  • Raw material test certificates
  • Purchase records
  • Test equipment list
  • Batch test reports
  • TG (Technical File)
  • Flamepath measurement reports
  • Employee qualification/skill matrix

πŸ”Ή 6. Common Reasons for Audit Failure

❌ Flamepath machining errors
❌ Lack of calibration
❌ No batch test reports
❌ Unauthorized design changes
❌ Poor traceability system
❌ QMS not updated
❌ Production vs. drawing mismatch
❌ Fabricated test reports
❌ Non-certified raw materials

πŸ”Ή 7. How to Prepare for DGMS Factory Audit (Checklist)

βœ” Ensure ALL drawings are DGMS approved

βœ” Maintain proper calibration records

βœ” Keep dedicated gauges for flamepaths

βœ” Maintain raw material certification

βœ” Ensure batch-wise QC records

βœ” Provide traceability of every component

βœ” Train QC inspectors & operators

βœ” Keep production as per QMS manual

πŸ”₯ 25 MCQs (DGMS Pattern) with Answers

1) Factory audit requirement comes from β€” a) Appendix VI
b) Appendix XIX
c) CMR 2017
d) Indian Standards
e) None
Ans: b

2) DGMS audit checks β€”

a) GST
b) HR files
c) Manufacturing & testing
d) Parking area
e) None
Ans: c

3) Calibration records must be β€”

a) Optional
b) Mandatory
c) Rare
d) Weekly only
e) None
Ans: b

4) ISO required for DGMS approval β€”

a) ISO 22000
b) ISO 27001
c) ISO 9001
d) ISO 45001
e) None
Ans: c

5) Ex equipment drawings must be β€”

a) Verbal
b) DGMS approved
c) Hand-sketched
d) Suggested only
e) None
Ans: b

6) Flamepath finish should be β€”

a) Rough
b) Painted
c) Smooth (Ra ≀ 6.3 ΞΌm)
d) Cracked
e) None
Ans: c

7) Unauthorized design change leads to β€”

a) Discount
b) Promotion
c) Rejection/withdrawal
d) Team party
e) None
Ans: c

8) Test equipment must be β€”

a) Random
b) Calibrated
c) Broken
d) Cheap
e) None
Ans: b

9) QAR stands for β€”

a) Quality Alteration Reference
b) Quality Assurance Report
c) Quantity Audit Result
d) Quota Adjustment Rule
Ans: b

10) Factory audit ensures β€”

a) Festivals
b) Employee leave
c) Production matches approved drawings
d) Salaries
e) None
Ans: c

11) PCB changes need β€”

a) No permission
b) Fresh DGMS approval
c) Manager approval
d) Storekeeper permission
e) None
Ans: b

12) Flamepath measured using β€”

a) Tape
b) Rope
c) Feeler gauges/micrometers
d) Colour card
e) None
Ans: c

13) Raw material certificate ensures β€”

a) Colour
b) Smell
c) Weight
d) Correct grade used
e) None
Ans: d

14) Field trial data required for β€”

a) First approval
b) Renewal
c) GST audit
d) Factory layout
e) None
Ans: b

15) DGMS checks QMS β€”

a) Monthly
b) Sometimes
c) During audit
d) Every day
Ans: c

16) Batch testing is β€”

a) Optional
b) Mandatory
c) Not needed
d) Temporary
Ans: b

17) Flameproof test facility required for β€”

a) Footwear
b) Ex-d equipment
c) Gas cylinders
d) Uniforms
Ans: b

18) Test reports must be β€”

a) Editable
b) Original & signed
c) Only photocopies
d) Verbal
Ans: b

19) Factory audit fails if β€”

a) Machines working
b) Drawings correct
c) Calibration outdated
d) QMS updated
Ans: c

20) Production deviation from drawing β€”

a) Allowed
b) Forbidden
c) Encouraged
d) Free
Ans: b

21) Material traceability used for β€”

a) Decoration
b) Music
c) Fun
d) Tracking materials used
Ans: d

22) Testing infrastructure includes β€”

a) Toy tools
b) HV tester, gauges, pressure test
c) Paint brushes
d) Fans
Ans: b

23) Factory layout part of β€”

a) Finance
b) QMS documentation
c) Housekeeping
d) Labour law
Ans: b

24) DGMS audit team looks for β€”

a) Company profit
b) Employee holidays
c) Compliance & safety
d) Office chairs
Ans: c

25) Purpose of DGMS factory audit β€”

a) Increase sales
b) Reduce workers
c) Ensure safe & compliant manufacturing
d) Save electricity
Ans: c

πŸ”š Conclusion 

DGMS Factory Inspection (Appendix XIX) ensures that equipment is manufactured with proper quality, safety, calibration & control.
A high-quality audit system ensures:
  • Zero design deviation
  • Authentic testing
  • Reliable performance
  • Safe use in gassy mines
Every manufacturer must follow Appendix XIX to avoid rejection, suspension or withdrawal of DGMS approval.

πŸš€ Download DGMS Factory Audit Notes at OnlineMiningExam.com
πŸ“ Practice 10,000+ DGMS MCQs
πŸ”” Join OME Telegram Channel for daily DGMS updates


{{ONLINEMININGEXAM.COM}}
India's 1st Online Mining Academy Prepare for DGMS 1st Class & 2nd Class Mining Manager......


OUR COURSES View More

/* Banner container */ #omxBanner { position: fixed; left: 50%; bottom: -120px; /* hidden initially */ transform: translateX(-50%); width: min(980px, calc(100% - 20px)); max-width: 980px; background: linear-gradient(90deg,#0f172a,#0b84ff); color: #fff; border-radius: 12px 12px 8px 8px; padding: 11px 14px; /* reduced (80%) */ box-shadow: 0 12px 30px rgba(3,10,30,0.45); display: flex; gap: 10px; align-items: center; z-index: 2000; transition: bottom 450ms cubic-bezier(.2,.9,.3,1), transform 250ms; font-family: system-ui, -apple-system, "Segoe UI", Roboto, "Helvetica Neue", Arial; } /* Show class slides banner up */ #omxBanner.show { bottom: 20px; } /* Left: icon / logo */ #omxBanner .left { flex: 0 0 51px; /* 80% of 64px */ height: 51px; border-radius: 6px; background: linear-gradient(135deg,#00d4ff,#0077ff); display:flex; align-items:center; justify-content:center; font-weight:700; color:#002; font-size:16px; /* reduced */ } /* Middle: text */ #omxBanner .center { flex: 1 1 auto; min-width: 0; } #omxBanner .center h4 { margin: 0 0 3px 0; font-size: 13px; /* reduced */ line-height: 1.1; letter-spacing: 0.2px; } #omxBanner .center p { margin: 0; font-size: 11px; /* reduced */ opacity: 0.95; } /* Right: CTA & close */ #omxBanner .right { display:flex; gap:6px; align-items:center; } #omxBanner .cta { background: linear-gradient(90deg,#ffb703,#fb8500); color: #07122a; border: none; padding: 8px 11px; /* reduced */ border-radius: 6px; font-weight: 700; cursor: pointer; text-decoration: none; font-size: 12px; /* reduced */ box-shadow: 0 6px 14px rgba(251,133,0,0.22); } #omxBanner .cta:active { transform: translateY(1px); } #omxBanner .closeBtn { background: transparent; border: none; color: rgba(255,255,255,0.9); font-size: 16px; /* reduced */ cursor: pointer; padding: 4px; line-height:1; } /* Mobile tweaks */ @media (max-width:600px) { #omxBanner { flex-direction: column; gap:6px; align-items:flex-start; padding:9px; bottom: 10px; width: calc(100% - 18px); left: 50%; transform: translateX(-50%); } #omxBanner .left { display:none; } #omxBanner .right { width:100%; justify-content: space-between; } #omxBanner .cta { width:48%; text-align:center; padding:8px 6px; font-size:11px; } }